When the release rule holds, the orchestrator makes the milestone's proposed files the specification and publishes a CanonBall.
- Who
- Program: Orchestrator
- Reads
Verification Record- Writes
spec/roadmap/archive/roadmap/index.mdCANONBALLS.md- In the repo
- See exactly what this station changed 8ca1c6a…75ac2f0
What arrives
A reviewed milestone arrives. At this station neither a person nor an agent decides anything; the orchestrator applies a rule.
The release rule
Checks for a milestone run against the release candidate: spec/ with the milestone’s proposed files applied. The milestone may be released when two things are true of the Verification Record computed for that candidate.
- Every clause the milestone touches is accepted.
- No clause it did not touch has become worse, unless a named person accepted that at the release gate.
The second condition protects everything already promised. A milestone carries no list of things it must not break, because the Record checks every clause every time.
spec/canon/- REQ-012
- INV-004
- ENV-003
- ASM-011
roadmap/M2-faster-small-refunds/diff/canon/- DEC-031
spec/canon/- REQ-012
- INV-004
- ENV-003
- ASM-011
- DEC-031
What the orchestrator does
When the rule holds and the review has passed, the orchestrator:
- copies the files in
diff/over the files of the same name inspec/; - archives the milestone folder in
roadmap/archive/; - records a CanonBall in
CANONBALLS.md, naming the build it releases; - tells the team to commit the result, tag it, and deploy that build.
For M2 this is one command, tools/canonball release M2-faster-small-refunds, and the same commit moves M2 to Released in roadmap/index.md. If another milestone was released in the meantime, the release candidate is the new spec/ with this milestone’s files applied, and the rule is applied to that candidate before anything is copied.
No person edits spec/ by hand, so spec/ describes the system as released and as supported by evidence. How the build is rolled out and rolled back is the pipeline’s job; CanonBall says which build goes out and what it promises.
What a CanonBall holds
## CanonBall 13
- released: 2026-03-10
- from: roadmap/archive/M2-faster-small-refunds
- build: 8ca1c6a
- record: 4 accepted, 1 accepted, with stated risk
- adds or changes: DEC-031 Auto-approve under $100
The entry names the build, the commit the review signed off, and the canon is spec/canon at the commit that records the entry.
A CanonBall fixes together, at one moment, what the system promises, the code that keeps the promises, and the evidence that it does. Together they answer the question “what does this system promise, and how do you know?” without anyone reading code. What a CanonBall is describes the format in full.
The one clause “accepted, with stated risk” is ASM-011, the assumption about the payment gateway. It cannot be proven from inside the system, so it is watched in production.
When the rule does not hold
The milestone stays on the belt. The Record names the clause that is holding it and the part of that clause with no evidence, so the work goes back to a specific place.
| What the Record shows | Where the milestone goes |
|---|---|
| A touched clause is unsupported | Verify, for the missing evidence |
| A check fails | Build |
| An untouched clause got worse | Build, or Review if someone means to accept it |
Whether a milestone is done is therefore computed from the evidence rather than judged by opinion.
What leaves
spec/ now describes a system in which small refunds are approved automatically, and that system is running as CanonBall 13. From here it is operated.